2023 Annual Project Manager Report

Reserve Number Updates

              I have been continually establishing stronger relationships with contractors, as well as, collecting numerous proposals to update the expenses on the major items that are required for GRCA to maintain and upgrade. With those findings, I worked with LCM Property Management and members of the Board to update the replacement costs associated with those items to reflect a more current budget for us to use when saving and scheduling for those repairs/replacements/etc. This is an ongoing project to assist with maintaining an updated budget for expenses.

Boiler Maintenance Program

The semi-annual maintenance program that coincides with the maintenance staff’s regular care of the boiler systems has assisted us in keeping the older boilers running smoothly to lengthen their life expectancy.

New Boilers

GRCA purchased 3 new boilers for building 9 at 1250 Golden Circle. The last 2 boilers and plumbing have been installed. Some minor pieces to the system are in the process of being completed for a full replacement for that building. The parts from this building’s old boilers will be repurposed to rebuild the boilers in building 10 at 1200 Golden Circle as they previously share the same models of boilers. This is in hopes to gain more lifespan for those boilers and push the new boiler purchase for that building out for a longer time period.

Building Foundations/Crawl Space Reports

With the structural engineering reports, we have been working hard over the past few months to get the high priority and medium priority lists repaired throughout the GRCA community. As we stated last year, nothing was found in the buildings that was to be cause of any alarm. The items were to stabilize any issues, add blocking, brackets, and joist sistering to maintain all areas from possible movement. We are ahead of schedule for fixing these repairs and currently have the low priority items remaining that we are budgeting into the first part of 2024. This will put us in a great spot for possibly eliminating future issues anytime soon and give us a stronger basis to analyze the buildings structurally going forward.

Parking Lots

July and early August we patched more pot holes in the parking lots and created a safer platform for everyone to drive and walk. We added a crack sealant to most of the cracking that was ell established in the parking lots to assist with keeping the heavy rains and snow melt from getting deep under the asphalt creating more pot holes, weak areas, heavy cracking. The hope was to assist with prolonging many areas where the parking lots are not in bad shape and save some of the future repair funds for replacements. With the costs associated with tearing out and repaving the entire complex, we believed that this was the best alternative until we get the budget established.

Gym Remodel & New Equipment

Late 2022 until Mid 2023, I did some remodeling to the exercise facility. I took a dividing wall out to open up a large area that was barely used previously, repainted the main room, added more rubber floor mats, mirrors, newer equipment I found from closing gyms and Marketplaces to replace the old, weathered benches and machines that were duck taped to keep the vinyl together, added a lot of new types of machines and equipment to broaden everyone’s types of workout routines. I was able to get a hold of some very expensive equipment at a very reduced cost or that I got for free to donate to the community. I spent a lot of hours searching, gathering, and saving money to create a more joyous atmosphere. This has now became a huge staple for the community connections and greatly assists the property values of everyone owning a condominium here at GRCA.

Saved over $21,743.75 on remodeling and equipment costs.

Sidewalks

We have been very diligent on keeping up with the sidewalks to eliminate any trip hazards throughout the complex. With that we completely poured new sections, leveled some areas were possible, manually ground down a lot of sections all dependent on locations and costs at the time. We have few areas still remaining to replace once we can get cement costs down and some savings in place.

Saved thousands on not replacing numerous sections

Exterior Stucco Repairs

I have been viewing over the past couple of years,, we have had some stucco issues with pockets pulling off the walls. We just finished up those building issues in late August of 2023.

Exterior Railings

We have been painting the exterior entrance railings at the low rise buildings due to rust and damage to eliminate any safety hazards from deterioration. This will be an ongoing item, on an as per needed basis and they are being viewed on a regular basis as part of my walk through evaluations.

Fire Safety Systems

We had a fire safety company come out to give us a full inspection report and make any repairs if needed to the high rise building’s fire safety systems. This report will be good for at least a 5-year period to completely satisfy all regulations. Also, we have a semi-annual inspection of all fire extinguishers to make sure all are current and working properly. Within the last week of September we will be having our annual heat sensor checks for the low-rise buildings per the City of Golden Fire Department.

Tree Services

GRCA had problems with a couple of insects destroying our trees last year. Emarald Ash Borer and Beetles were causing a lot of trees to start dying. We started the maintenance plan for soil injections to be done to save the trees as much as possible. We treated over 80 trees within the community, but had some that were beyond saving. My plan is to have add additional trees planted to replace those that were lost.

Savings of $7,615 from other providers

Carpet Cleaning Building Hallways

We had budgeted for all the hallways and common areas to have carpet cleaning services done for $8,278. I decided that most of the hallways looked good and mapped out a spot cleaning plan to be completed. Since there are large minimums for carpet cleaning companies, I purchased a small carpet cleaner for $150 and have an office staff member assist with spots when a problem comes up. We are seeing an increase over the past few months in residents carrying their leaking garbage down the halls and creating stains everywhere instead of handling the issue inside their units or carrying the entire garbage can outside. Please assist us in maintaining a clean building.

Savings of over $7,000. but will be reduced with the increase in problems areas from residents.

Floor Mats

GRCA had Cintas for our rugs in all of the buildings. They came once a month to change out the rugs and replace with clean rugs. They were increasing the costs of the contract that does not end until 2025. I purchased new interior and exterior rugs to handle ourselves and reduced the contract to meet minimal requirements until the end of the contract. This plan has been very successful. We have only had to replace a few throw carpets and were able to maintain the budgeted savings.

Previous: $9,742.32/yr

New increase: $11,548.32/yr

Cost of Mats: $2,642.52

Cost savings first year = $7,165.80, cost savings second year = $9,808.32. After January of 2025 = $11,548.32

Common Area Windows

We hired a glass company to replace the glass in a lot of common area windows that were cracked, graffitied, scratched. We still are circling back to make sure they were sealed properly and painting to protect the wood. Eventually it would be nice to phase in changing all of those windows to vinyl in the future.

PROJECTS in the WORKS

Tree/Landscaping

With the storms and bugs that ruined some of our landscaping, I am working on planting some new landscaping and trees this Fall to replace those that we have lost.

Gym Backroom Opening

The plan is to create a half wall in the back area of the gym to open up the area for more exercise space. For now we will be removing the door only to allow access to the area in hopes to complete the remodel sometime within the next few months.

FUTURE PLANS

Sprinkler System

The old system has been struggling with many repairs throughout the years and it is time to get the system upgraded and new lines, heads, etc installed. This would assist with wasted time with repairs, added expenses that keep rising due to the age of the current system, and make the watering more efficient which should save us on water bills and conservation of water at the same time. This year’s repairs increased by thousands that could go into the new system. This project got pushed due to other larger and pressing issues (such as boilers and crawl space repairs). Hopes are to begin before Spring of 2024. We also had Resource Central come do a FREE sprinkler evaluation at the end of August to assist with determining where we could better conserve water, etc. We plan to use their findings to map out a better sprinkler system. A full replacement was approximately $120,000 (which would include adding sprinklers to the field grass areas along Heritage Rd.). All would be scheduled in 2-3 phases.

Swamp Coolers

1150 and 1200 Golden Circle have been having some issues this Summer. We were able to put a new motor on each to make it through the Spring/Summer months but 1150 Golden was not able to keep up as well with pumping cold air into the halls. We are asking ALL RESIDENTS to keep ALL DOORS into the halls closed when not in use. Trying to pull air from the halls to cool each condominium unit puts added stress to the motors on the swamp cooler. Also, the Fire Department states that this is a HUGE safety concern with fire doors and back drafts from units causing a larger fire that could be avoided. The heat will be on fully soon enough and we can analyze them before Spring 2024 when we should have a better budget for replacements.

Pool Deck Replacement

The pool decking has been cracking and splitting from the changes in the weather over the years and is past the time for a full replacement. We have been patching areas of the decking for many seasons and has roughly made it through the swim season, the deterioration has been getting worse. Plans were in place to replace the pool decking both inside and outside this past Spring of 2023 but got put on hold due to the New Boilers this year and work on the Crawlspace. Hope are to reevaluate for Spring 2024.

FUTURE IDEAS

Garage Doors

Researching the prospective ideas of adding garage doors to the pool area and the gym buildings as part of remodeling projects. The pool garage door would allow for residents to swim laps freely, allow more air flow, and create a resort type atmosphere for a full open room concept. The gym project would allow fresh air, more lighting into the building, and give access to an outdoor gym area.

Outdoor Seating Areas

I would like to add some outdoor seating areas throughout the community to provide a comfortable environment for everyone to come outside and enjoy the 24+ acres that we conveniently have at our disposal. These would include hanging swings, hammock hookups, and gas firepits.

Main Entrance Remodeling

Ideas for a new facelift for the main entrance have been on my mind for a while. Was looking at moving the GRCA sign to the center island, create a lite raised flower bed area surrounding the sign. And on both sides of the drive way, creating new landscape that would include raised flower beds (using large stones and metal), trees, sound barriers berms, Colorado flowers that are all easily maintained.

Dog Run

There has been a piece of the property that would work greatly for a new dog run area on the South/East side of the pond. With the possibility of selling off the property near 4th Ave., a more dog friendly area would work best to allow your fury friends a place to run freely, safely, and legally off lease.